Tuesday, July 31, 2012

Nightstand Progress Blog 7 Quiet Rock

Exciting to come into the building today as two studios, along with the green rooms and office areas have all been sheetrocked. Today Quiet Rock has been installed in 2 of our 4 studios, with Studio C and the recording studio to commence tomorrow.
Check out the shots of Studios A and B below. Getting CLOSE!

Wednesday, July 18, 2012

Nightstand Studio Progress Blog 6

After a couple weeks of precision work that was not quite that demonstrative of progress, we are ready for the big push of insulation and drywalling and finally closing in the working spaces. HVAC interior work is done, the rough plumbing and electric is done, and the truckload of soundproofing insulation has been delivered. Insulation to commence tomorrow, and drywall to commence on Monday!
Pretty soon, lights, camera, action!

Pics of HVAC, our approved inspection, and the 8 skids of insulation below!